Deployment 2012 to 2013:
WH300 ADCP


Deployment summary:
Duration: deployed from Oct 16, 2012 to Oct 16, 2013
Location: 71° 23.64' N, 152° 2.91 W in 147 meters of water
Variables measured:zonal, meridional velocity
Sensor information: 300KHz WorkHorse by RDInstruments ser# 1393.
Initial: contained in the matlab file aon12_bs3a_Final1.mat
    the data format is described in readme_format_aon12_bs3a.txt .


We originally planned to re-deploy the 2011-2012 WH300 #2226. However, when inspecting the recovered dataset on the 2012 cruise, we found beam 4 to be dead. Therefore, we instead deployed a loaner from Glen Gawarkiewicz that had been taken along as a spare if needed.

Upon recovery in 2013, #1393' clock had drifted (lost) 7 minutes 42 seconds.


Data processing:

The final data were provided by Dan Torres, who described the processing in the file process_steps_aon12_bs3a.txt.